ASA RIVER DAM


Situated just outside IlorinKwara State capital city, Asa River Dam was constructed by Julius Berger Nigeria PLC in order to increase the supply of potable water by approximately 50,000 cubic metres per day, to the towns within the state.
Asa River Dam consists of three sections: (1). a 400m long earth fill dam, (2). a 150m long concrete gravity dam and (3) a lateral earth dam with a length of 160m.
The earth fill dam at 26m high above the bottom of the Asa River and has a width of 150m at the dam foot and of 5m at the crest.
The concrete gravity dam is 20m high and has a width of 12m at the foot and of 3m at the crest. The lateral earth dam is 6m high and 23m wide at the foot.


Considering the size of the Asa river’s catchment area, the 60 meter wide spillway was designed for a volume of 1,300 cubic metres per second. A 65m long weir bridge was built over the spillway.
During the design phase, Julius Berger Nigeria PLC proposed to raise the height of the spillway by one metre. This resulted in an increased dam capacity of up to 44 million cubic metres.
In order to obtain a better smooth and dense surface, prefabricated concrete units were used for the construction of the downward side of the spillway. These units served as form work for the concrete of the weir.
For economical reasons and to reduce hydration heat to a minimum, waterproof concrete only 1.0 metre thick was used for the construction of the gravity dam on both the upstream and downstream side.
Unreinforced concrete was used for the core. A drinking water treatment plant with a capacity of 2,300 m³ per hour was built with precast concrete units.
The project also included two 40m diameter elevated water tank with a storage capacity of 10,000 m³ each and one 29m diameter elevated pre-stressed concrete tank. A total of 300,000m³ of dam material, 36,000m³ of concrete and 620 tons of steel were used for this project.

DAM USAGE

The purpose for the dam include improvement of water supply to Ilorin and other towns and settlements along the river system as well as irrigation, fisheries and livestock development and recreation.

HYDRO POWER POTENTIAL

The dam was designed with the potential for hydro power generation in mind, and may have a capacity of 3MW on average – more in the rainy season and less in dry season.
However, power would cost considerably more to deliver than current retail prices, and it is not clear how a project to install the generating equipment would be financed.

ASA DAM CONFERENCE CENTRE AND RESORT

In a bid to further develop Kwara State’s tourism industry, the state government is inviting local and foreign investors to invest in a mixed-use development at Asa Dam.
Nestled on the banks of a bountiful reservoir, the Asa Dam Conference Centre and Resort Development will attract international dignitaries and travellers to Kwara State.
Whether visitors come to conduct business at the Conference Centre or relax with a round of world class golf, they will be immersed in the natural environment while enjoying the comforts of modern facilities.
This design solution strives to provide a dynamic experience without compromising the environmental, financial, or social sustainability of the site.

Comments

Popular posts from this blog

LASABI SACRED FOREST

LITA FOREST RESERVE

ERIN IJESHA WATERFALLS